Final steel shipment arrives for Johnson Street Bridge

Parts will be loaded onto a barge this afternoon, and transported under the current bridge Tuesday
8553865_web1_170920-vne-johnsonststeel01
The new Johnson Street bridge deck span is prepared for offloading onto a barge at Ogden Point on Monday afternoon. The shipment was scheduled to be offloaded in Victoria’s upper harbour either later Monday or Tuesday followed by the assembly process. Photo courtesy City of Victoria

The final shipment of steel for the Johnson Street Bridge arrived at Ogden Point terminal last night and is being off-loaded onto a barge this afternoon.

The AAL Singapore arrived off Port Renfrew from Shanghai after starting its journey across the Pacific Ocean on Aug. 30. The steel components include the bridge deck span to be used by vehicle and bicycle traffic, as well as pedestrian and multi-use pathways.

RELATED: Steel shipment draws attention

The barge will be transported through the Inner Harbour and the existing bridge crossing. Once the span is cleaned and inspected for possible shipping damage, the walkway and multi-use path will be attached to the span. Workers will then install the bridge architectural and traffic lighting and the new bridge deck surface.

This is the second shipment of large, manufactured steel components. The first arrived Aug. 20, with the north and south rings, lower counterweight and temporary structure to prop up the bridge while it is being built.

RELATED: Johnson Street Bridge contractor requests more cash from Victoria

Now that all the parts have arrived, the remainder of work on the bridge will be done locally. Project manager Jonathan Huggett said last month that by Christmas, the bridge should “look almost complete.”

The project is on track to be ready for public use by March 31, 2018 after multiple delays.

RELATED: Johnson Street Bridge delay may not be the last